MDE-4298D CFN Series Site Controller III Installation Manual · September 2009 Page 79
Manual Override Test Testing
11 Turn off the breakers for all pumps and/or remote dispensers and the SC and other
components.
12 Replace all wiring connectors (green) previously removed from the Pump Control I/O PCB
assembly.
Note: The manual override test will uncover most point-to-point AC wiring mistakes that can
occur. The automatic test performed during the system startup will complete the
verification of correct AC wiring to the pump/remote dispensers. The automatic test
should only be performed at the startup.